Sunday, May 18, 2014

Clipping Coupons and More!

One of my friends was frantically searching for specific coupons and her scissors were zipping along the dotted lines in the newspaper. Clipping coupons is a past-time for many households: Big coupons, small coupons, coupons with special requirements, coupons worth 25 cents and coupons worth one dollar are clipped. We clip the coupons to save money while purchasing items we need or items we want to try.

Everyone wants to get the most out of their money and Columbia School District is no exception. As we proceed through the bond projects we will carefully analyze each and every aspect of the project to ensure it will benefit our students and our community. The basic guide to our projects is the original State of Michigan Treasury document that outlines the bond based upon our facilities analysis that was completed last spring and summer.

During the Bond Issue campaign we used the slogan: Safe, Warm, Dry and Smart. This summer our projects will include elements of: Safe, Dry and Smart.

Safe projects to be completed this summer include: (1) The bus drive east of the middle school will come up and terminate in a bus parking area at the east end of the current CMS/CES parking area. (2) The parent drop off loop will go from west to east along School Street between the elementary and middle school. (3) The parent drop off loop will also contain a parking area for preschool parents and visitors. (4) There will be a new parking area for elementary parents and staff members at the west end of the elementary school. This parking lot will eliminate the need for parents and children to cross School Street. (5) The parking lot west of the middle school will become parent and staff parking for the middle school to eliminate the need for parents and students to cross School Street. (6) The gravel parking lot west of the middle school will be upgraded. (7) The Columbia Middle School campus, which will become an area for third through sixth graders in the fall of 2015, will receive a new playground, improved fencing, and upgraded walking path around the football field. (8) The Columbia Elementary playground will receive an upgraded walking path. (9) There will be new lighting for the parent drop off area between the middle and elementary schools. (10) There will be two additional fire hydrants on the CMS/CES campus.

The Dry projects for the summer of 2015 include new roofs, gutters and flashing for Columbia Central High School, Columbia Middle School, Columbia Elementary School and Columbia Options High School.

Smart projects include: (1) The purchase of several carts of Chromebooks for CCHS and CMS students and an additional iPad cart for CES. The carts will have wireless access points that will later be used during the upgrading of the wireless infrastructure at CCHS, CMS and CES. (2) The relocation of the CCHS Presentation Lab computers to the current Media Center Lab, and the relocation of the Media Center computers to the south end of the Media Center.

At this point the bid package for fall 2014 projects, which will go out to bid early this summer, will include Smart and Safe renovations: (1) The south wing of Columbia Central High School (the old shop wing) will be renovated to accommodate seventh and eighth grade students in the fall of 2015. (2) There will be initial wiring for upgraded technology. (3) There will be a bid for the separation of bus, parent and student traffic at CCHS.

At this time we are planning for the balance of the projects will go out to bid in approximately January of 2015 and will feature Warm, Safe, Dry and Smart elements including: new heating and cooling for all educational facilities, renovation of all educational facilities, upgrading the technology infrastructure at all buildings, addition of locker rooms for seventh and eighth grade students at CCHS, upgraded parking facilities at CCHS and Options High School, and the balance of projects included in the bond issue.

As we go through the renovation improvement process we will continue to have Facility Improvement Team meetings during which we will give updates regarding the progression of the projects. The meetings will be advertised on our website, the Columbia School District Facebook and the Restore the Soar Facebook page. Elements of the project will be outlined on the Restore the Soar Facebook page and the projects webpage. There will also be updates given at our monthly school board meetings, which are on the second Monday of each month in the Community Room of CCHS at 7 pm.

If you have any questions or would like to know how to register your child for one of our great Columbia Schools, please call me at 5175926641 or email me at pam.campbell@myeagles.org.